Engineering Installation Engineering Installation
Team Working Towards a Sustainable Future 01527 893880

Charlton Lane Centre

Client: 2gether NHS Foundation Trust
End User: Charlton Lane Centre
Project Description: Strip out, remodelling & extension of existing mental health unit to create new elderly persons mental health centre
Services Provided by ESDP: Mechanical and electrical design and site monitoring services for strip out and enabling works. Performance design to a high level for fit-out contract, and comment on D&B Contractor's design.
Design Features: Provision of integrated nurse call and dementia care assistive technologies with DECT handset provision. Building wide lighting control system, with the facility to remotely control the lighting, isolate power and domestic water services to patient bedrooms. Access control system to patient and staff area doors, with central PC control. Multi-stage fire alarm with cause and effect for phased evacuation.
Project Construction Value: £6,000,000
Completion: August 2010